Resource-Limited Schedule
A project schedule whose schedule activity, scheduled start dates and scheduled finish dates reflect expected resource availability. A resource-limited schedule does not have any early or late start or finish dates. The resource-limited schedule total float is determined by calculating the difference between the critical path method late finish date* and the resource-limited scheduled finish date. Sometimes called resource-constrained schedule. See also resource leveling.