Remaining Duration
The amount of time required to complete the unfinished portion of a task. With a value for an actual duration, it is calculated as: Remaining duration = duration - actual duration
If a % complete value is entered for the task, it is calculated as: Remaining duration = duration - (duration * % complete)
Remaining duration values can also be entered against tasks, recalculating the task's duration and percent complete values.