Welcome to PMConnection

     

Menu
· Home
· The Project Management Search Engine
· Exclusive Articles

Related Sites
There isn't content right now for this block.

Related Products
   
 

The Self-Driving Project: Using Artificial Intelligence to Deliver Project Success

 
  
 
Citizen Development: The Handbook for Creators and Change Makers
  
 
 
A Guide to the Project Management Body of Knowledge: PMBOK 7th Edition 2021
  

 
PMP Project Management Professional Exam Study Guide
    
 

 
Microsoft Project Step by Step


  

 
Microsoft Project
  

  

 
Managing Enterprise Projects: Using Project Online and Microsoft Project Server

MS Project: Creating a Dynamic Project Buffer in Microsoft Project
Posted on Saturday, January 26 @ 00:30:53 EST by webadmin

PMConnection Articles
This article is Part 2 of a series of articles that describes a process used to develop a project schedule.

Using the PERT feature of MS Project and collecting three duration estimates allowed us to develop a schedule that lacked most of the “padding” that was generally incorporated into previous task duration estimates. See previous article on how we did this.

The output of running the PERT feature in MS Project translated into the project being 344 days in duration and finishing on 4/26/05.

Buffer1


But within the same schedule I could also see the “Worst Case” scenario. To do this, I simply clicked on the Pessimistic Gantt Option within the PERT Analysis toolbar

Buffer2

When choosing this option, I could see the Pessimistic Duration and Pessimistic Finish. The Pessimistic Duration was 381 days and the Pessimistic Finish was 6/16/05.

You will also notice that within this view, the current Finish and the Pessimistic Finish are side by side. I kept looking at those two finish dates. The more I looked at them, the more uncomfortable I became.

Buffer3

First off, there was nearly a two month difference between current Finish (generated from PERT calculations) and the Pessimistic Finish. This seemed like a long time. But then I got to thinking; this project is going to take nearly a year. This two month delay would only happen if all of the things went wrong that everyone had anticipated. And, given the track record of projects within this company, a two month delay in a year long project would actually be below the average! That made me feel a bit better, but remember, this project had to be better.

The second thing that bothered me was this two month difference was based upon known possible delays. I got to thinking a bit more, and realized that these known delays could actually be called “Risks” to my project schedule. Unfortunately, given the project management maturity level of our organization, we did not perform any formal Risk Analysis, nor was there a process for incorporating those risks into our schedules.

As I packed up my stuff to leave the office for the evening I thought: “I wish there was some way I could incorporate these risks into my schedule.” I knew the stakeholder review meeting was just a few days away and at that time the milestone and project finish dates that we show would be as good as cast in stone!

That evening found me at a local MPA (Microsoft Project Associate) meeting. The event is always a good time. I got to see a few of my peers and swap war stories. But the best part for me was the presenter. She gave an overview of “How to build a Dynamic Project Buffer into Your Microsoft Project Schedule”.

She started off her presentation by defining buffers. Buffers, also called Contingency Reserves, or Time Reserves can be incorporated into the project schedule as a recognition of schedule risk. I just about fell out of my chair! This is exactly what I needed to know. She went on to say that buffers are additional time that is added to the schedule. It can be derived by:

a) a percentage of the estimated activity duration,

b) a fixed number of work periods, or

c) developed by quantitative schedule risk analysis.

She said this information could be found in PMBOK (3rd Edition)on page 142.

Before diving into the actual “how to” using Microsoft Project, she talked a bit about something called “Critical Chain”. She said this was a scheduling concept unearthed in a book called “The Goal” by Eliyahu M. Goldratt. She also stated some information could be found on this concept in the newest version of PMBOK on page 147. She made it clear that what she was about to show was “How to Build a Dynamic Project Buffer into Your Microsoft Project Schedule” and not true Critical Chain project management.

She then opened up the following schedule:

Buffer4


She explained that a Project Buffer gets added at the end of the critical path of a project. She then inserted the Project Buffer. She used 3 days for the Project Buffer Duration:

Buffer5


She changed the logic of the schedule to include the Project Buffer:

Buffer6


She then copied the Finish date for task 10, placed the cursor on the Start date for the Project Buffer and Pasted Special, then chose Paste Link:

Buffer7


Then she clicked on OK. She also made it a point to show us the little indicator in the bottom right corner of Start for Project Buffer. This indicates the cell is linked.

Buffer8


She then copied the Start date for Project Complete, moved her cursor to the Finish date for Project Buffer and again chose Paste Special, Paste Link:

Buffer9


After clicking OK, she removed the predecessor for the Project Buffer:

Buffer10


Next, she demonstrated how the dynamic Project Buffer works. This sample project had a Project Completion date of 2/18/04 and a 3 day Project Buffer. She changed the duration of Task 2 from 5 days to 6 days and the duration of the Project Buffer automatically reduced from 3 days to 2 days:

Buffer11


“Let’s have another task slip” she said, and changed the duration of Task 3 to 7 days. Again, the Project Buffer reduced:

Buffer12


With this second delay, we have used up all the Project Buffer. The Duration is now 0 days. So what happens if we have another slip? She then changed Task 1 in Phase B to 6 days:

Buffer13

Now the over-all Project Completion date slipped to 2/19/04.


“This is awesome”, I thought. Using this approach will resolve my concerns. I will create a Project Buffer for my project with a duration of two months (the difference between the Pessimistic Finish and the current Finish). I can even call this our Project Risk Buffer. This will work!! I headed home for the evening.

Be sure to read next months article about what happened when I took this concept to management.






 
Related Links
· More about PMConnection Articles
· News by webadmin


Most read story about PMConnection Articles:
300 Project Manager Interview Questions


Article Rating
Average Score: 4.46
Votes: 15


Please take a second and vote for this article:

Excellent
Very Good
Good
Regular
Bad


Options

 Printer Friendly Printer Friendly


Associated Topics

PMConnection Articles

Sorry, Comments are not available for this article.


Copyright 2005-2024 PMConnection.com. All Rights Reserved.
http://www.pmconnection.com a
PHP-Nuke Copyright © 2005 by Francisco Burzi. This is free software, and you may redistribute it under the GPL. PHP-Nuke comes with absolutely no warranty, for details, see the license.
Page Generation: 0.10 Seconds