Status
Description The Status field indicates the current status of a task, specifying whether the task is Complete, On Schedule, Late, or a Future Task. How Calculated If the task is 100 percent complete, then Microsoft Office Project sets the Status field to Complete. If the task start date is greater than the status date, then the Status field contains Future Task. If timephased cumulative percent complete is spread to at least the day before the status date, then the Status field contains On Schedule. If the timephased cumulative percent complete does not reach midnight on the day before the status date, then the Status field contains Late.