Welcome to PMConnection

     

Menu
· Home
· The Project Management Search Engine
· Exclusive Articles

Related Sites
There isn't content right now for this block.

Related Products
   
 

The Self-Driving Project: Using Artificial Intelligence to Deliver Project Success

 
  
 
Citizen Development: The Handbook for Creators and Change Makers
  
 
 
A Guide to the Project Management Body of Knowledge: PMBOK 7th Edition 2021
  

 
PMP Project Management Professional Exam Study Guide
    
 

 
Microsoft Project Step by Step


  

 
Microsoft Project
  

  

 
Managing Enterprise Projects: Using Project Online and Microsoft Project Server

Flexible Constraint


As opposed to inflexible constraints, flexible ones schedule tasks as follows:


- Finish no earlier than (for projects scheduled from the project's start date).
- Finish no later than (for projects scheduled from the project's finish date).
- Start no earlier than (for projects scheduled from the project's start date).
- Start no later than (for projects scheduled from the project's finish date).

These constraints will not cause schedule conflicts if a task is delayed beyond its constrained date.



The Project Management Search Engine results here.







[ Go Back ]

Microsoft Project® Fields, Terms and Definitions

Copyright © by PMConnection - (6043 reads)

Encyclopedia ©


Copyright 2005-2024 PMConnection.com. All Rights Reserved.
http://www.pmconnection.com a
PHP-Nuke Copyright © 2005 by Francisco Burzi. This is free software, and you may redistribute it under the GPL. PHP-Nuke comes with absolutely no warranty, for details, see the license.
Page Generation: 0.08 Seconds