Contoured Assignment
An assignment where the hours are scheduled at a non-uniform rate. Microsoft Project's options include: Back loaded Front loaded Double peak Early peak Late peak Bell Turtle User-defined
All contoured assignments will take more time than a flat assignment (which is the default). Contours are displayed as timephased fields within the task usage and resource usage views.