CPI
Within earned value analysis, the Cost Performance Index. Calculated as the ratio of budgeted cost of work performed (BCWP) and actual cost of work performed (ACWP). CPI = BCWP/ACWP. If this value is 1 then the project, summary task or task is exactly on budget. If the value is less than 1, then things are over budget; greater than 1, things are ahead of budget. See also CV.