Inflexible Constraint
As opposed to flexible constraints, inflexible constraints schedule tasks as follows: - Finish no later than (for projects scheduled from the project's start date) - Must finish on (for all projects) - Must start on (for all projects)
If a task is delayed beyond its constrained date, an inflexible constraint can cause a scheduling conflict.