Multiple Critical Paths
Microsoft Project can calculate and display a critical path for each independent network of tasks within the project or program. This sets the late finish date for tasks without successors or constraints to be to be the same as their early finish date, thus becoming critical. A project-specific setting, this setting is set or cleared within the Calculation tab of the Options dialog box (Tools..Options).