Project Finish Date
The latest date for any work in a project plan to complete by. This date is normally calculated with a forward pass. It is relative to the project start date plus the longest schedule of tasks within the project. Resource leveling beyond slack can also determine this date. A project finish date can also be entered within the Project Information dialog, whereby all new tasks will be set as ALAP.