Updating Task Status Updates Resource Status
Selected, Microsoft Project will automatically calculate the actual work, remaining work and cost for resources assigned to a task relative to the tasks percent complete. Cleared, Microsoft Project will expect actual work and remaining work to be entered for both tasks and assignments. Set within the Calculation tab of the Options dialog box (Tools..Options).